Malawi - Local Government Development Project (anglais)

Project outcome is rated unsatisfactory. By today's standards of practice in the World Bank, the project objectives were not formulated clearly enough and were too ambitious. In particular, the objectives should have reflected a more realistic vision of what one project could accomplish, given the inherently risky nature of governance reforms, the severly limited implementation capacity of both the central and local governments, and the long time...