The Social and Infrastructure Relief (SIRP) Project in Guinera-Bissau was satisfactory. There is, nonetheless, a continuing need for assistance in the development of more detailed procedures and in fully implementing the introduction of the accounting system. The development of training facilities has for the various reasons been subject to major delay largely due to disputes arising between the various entities whom it was proposed should be responsible...