Skip to Main Navigation

Honduras - Sixth Power Project (anglais)

The Sixth Power Project consists of: (a) the extension to the Rio Lindo hydro plant, including four dams to divert three rivers in the Lake Yojoa area and construction of a new pipeline and penstock, as well as engineering and construction supervision of the works; (b) distribution system improvements for the three year period 1976-78; (c) extension of electricity supply to rural areas not presently served; (d) materials and equipment needed for system...