The development objective of the First Phase of the Dasu Hydropower Project for Pakistan is to facilitate the expansion of electricity supply of hydro-power in Pakistan. Some of the negative impacts and mitigation measures include: (1) Pakistani rupee (PKR) 1,120,000 for each tower as compensation for the land taken for each tower. The amount may vary from on one tower to another due to location and a variety of other factors; (2) cash compensation...