Nigeria - Electricity and Gas Improvement Project (anglais)

Ratings of Electricity and Gas Improvement Project for Nigeria were as follows: outcome was moderately unsatisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include:(i) Expanding the available upstream electricity supply by itself is not going to increase grid-based electricity consumption; (ii) The Accugas Partial Risk Guarantee (PRG) may have focused too narrowly...