Afghanistan - Kabul Aybak and Mazar-e-Sharif Power Project (anglais)

Ratings for the Kabul Aybak and Mazar-e-Sharif Power Project for Afghanistan were as follows: outcomes were unsatisfactory, risk to development outcome was high, Bank performance was unsatisfactory, and Grantee performance was unsatisfactory. Some lessons learned included: it is hard to avoid the impression that the project was seen as a means of adding funds to emergency power rehabilitation project (EPRP) for rehabilitation investments, based on...