Ratings for the Second Rural Access Project for Bhutan were as follows: outcomes were moderately satisfactory, the risk to development outcome was negligible to low, the Bank performance was moderately satisfactory, and the Borrower performance was satisfactory. Some lessons learned included: economic evaluation in a situation where low density populations live in mountainous terrain, the construction costs are high and economic benefits are low...