Ratings for the Public Financial Management Modernization Project for Belarus were as follows: outcomes were satisfactory, the Bank performance was satisfactory, and the monitoring and evaluation quality was substantial. Some lessons learned included: IFMIS implementation is often hampered by lack of clarity regarding system requirements, frequent change-orders and shortcomings in procurement and contact arrangements. To ameliorate these risks, and...