Ratings of Volta River Basin Strategic Action Program Implementation Project for Western Africa were as follows: outcome was unsatisfactory, Bank performance was moderately unsatisfactory, and monitoring and evaluation quality was modest. Some of the lessons learned include: (i) The capacity of the Volta Basin Authority (VBA) staff for Bank project implementation needed to be significantly improved; (ii) Because transboundary river basin interventions...
Voir la suite

INFORMATION

  • 2020/02/10

  • Bilan de fin d’exécution et de résultats

  • ICR4888

  • 1

  • 1

  • Western Africa,

  • 2020/03/06

  • Disclosed

  • Western Africa - Volta River Basin Strategic Action Program Implementation Project

  • Environmental and Social Management Framework