Ratings for the Giza North Power Project for Egypt were as follows: outcomes were satisfactory, the Bank performance was satisfactory, and the monitoring and evaluation (M &E)quality was substantial. Some lessons learned included: The primary lesson learned is the need to be agile and flexible so as to increase the impact of the project if or when opportunities emerge. In this particular case, when it became clear that additional generating capacity...