Ratings for the Bogota Second Power Distribution Project for Colombia were as follows: outcomes were unsatisfactory, project sustainability was likely, Bank performance was satisfactory, and Borrower performance was also a satisfactory. Some lessons learned included: a commitment to project implementation should be assured prior to project execution, both on the part of the Government and the Borrower; this commitment should translate into...