Ratings for the Local Government Support Program Project for Morocco were as follows: outcome and Bank performance was moderately satisfactory and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: having clear institutional arrangements upfront and clarifying beneficiary and government obligations for project management is key. Ensuring adequate resources to define a robust M and E framework at the design stage...