The Tenth and Eleventh Railway Projects in Pakistan was implemented. Implementation was very slow to take off. The Bank's supervision was flawed. It neglected to follow through on the planned "joint International...
The outcome of the Eleventh Railway Project for Pakistan was unsatisfactory. The project did not achieve its main objectives and was not completed, its impact was very modest, sustainability is not likely...
This press release announces the International Development Association (IDA), concessionary lending affiliate of the World Bank, has approved a credit of fifty million US dollars to Pakistan for an eleventh...
The Eleventh Railway Project is designed to improve the utilization of PR's existing assets and consists of the following main components: (a) improvement in locomotive maintenance through the introduction...
The Eleventh Railway Project is designed to improve the utilization of PR's existing assets and consists of the following main components: (a) improvement in locomotive maintenance through the introduction...