This Report was prepared by the World Bank Group (the WBG) Integrity Vice Presidency (INT). It provides the findings of an INT administrative inquiry (the Investigation) into allegations of corrupt, fraudulent...
The Second Transmission and Distribution Project for Vietnam received a moderately satisfactory outcome rating with moderate risk to development outcome. Both the Bank and Borrower received moderately...
This aide Memoire reported that a World Bank mission carried out an implementation support mission for the Second Transmission and Distribution Project (TD2) in Vietnam from June 3 to 11, 2013 and June...
The objectives of the Second Transmission and Distribution project for Vietnam are: a) alleviate power shortages and improve the quality of power supplies by improving transmission and distribution network...
This environmental management plan for the Vietnam Second Transmission and Distribution Project identifies potential environmental risks and proposes measures to mitigate them. Negative measures include:...
The objective of the Additional Financing for the Second Transmission and Distribution Project is to assist the borrower in developing efficient electricity transmission and distribution system, thus enabling...
The objective of the Second Transmission and Distribution Project is the efficient development of Vietnam's transmission and distribution system. The closing date for the will be extended from December...
The objective of the Second Transmission and Distribution Project is the efficient development of Vietnam's transmission and distribution system. The closing date for the will be extended from December...
This environmental management plan for the Vietnam Second Transmission and Distribution Project identifies potential environmental risks and proposes measures to mitigate them. Negative measures include:...